Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22BH0143 was awarded at 100.00% of its ABC. Across its 15 recorded contracts, MA TESORO CONST / EGB CONST CORP FORMERLY: EGB CONST was awarded at ≥99.5% of ABC 15 times (100.0%), versus 70.4% for flood-control contracts overall. This may be due to highly competitive bidding where the winning bid matches the ABC exactly.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure at Brgy. Papan Este, Jones, Isabela22BH0143Flood control | 100% | January 10, 2023 | November 21, 2022 | — | completedsumbong source |
Start: April 1, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Isabela 4th District Engineering Office",
"ratio": 1,
"abcPhp": 96500000,
"threshold": 0.995,
"contractId": "22BH0143",
"contractor": "MA TESORO CONST / EGB CONST CORP FORMERLY: EGB CONST",
"contractCostPhp": 96500000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to highly competitive bidding where the winning bid matches the ABC exactly.
