Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22PA0141 (₱96.50M) is recorded as completed in 64 days against 277 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.3%. The contractor may have deployed unusually large resources or worked in favorable conditions, allowing for rapid completion.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Malanas Flood Control Structure, Culliong, San Juan, Abra22PA0141Flood control | 100% | March 24, 2023 | August 23, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 20, 2022 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2022-06-20T00:00:00.000Z",
"contractId": "22PA0141",
"actualEndDate": "2022-08-23T00:00:00.000Z",
"targetEndDate": "2023-03-23T00:00:00.000Z",
"contractCostPhp": 96496036
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo