Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Pattern Consistent with Contract Splitting

Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: 7 contracts awarded to TJMT CONST by the same office started within 46 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 5 in the same municipality. It is possible these are separate flood control projects in different locations within the same area, each requiring its own contract.

Public record entityConstruction of Dummun River Revetment 1, R/S, Nabaccayan, Gattaran, Cagayan
LocationGATTARAN (CAGAYAN), CAGAYAN, Region IIContract 24BB0091
Amount₱49,000,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Dummun River Revetment 1, R/S, Nabaccayan, Gattaran, Cagayan24BB0091Flood control100%November 7, 2024November 7, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 22, 2024 · Source fetched October 21, 2026

Rule Definition

≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.

Triggering Data & citations

Cluster of contracts just under procurement threshold in one municipality

{
  "deo": "Cagayan 1st District Engineering Office",
  "contractId": "24BB0091",
  "contractor": "TJMT CONST",
  "windowDays": 120,
  "clusterSize": 7,
  "thresholdPhp": 50000000,
  "contractCostPhp": 49000000,
  "maxInOneMunicipality": 5
}

Cite this record

Love the Philippines. “Pattern Consistent with Contract Splitting (C5): Construction of Dummun River Revetment 1, R/S, Nabaccayan, Gattaran, Cagayan.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/6dc6afdd-95ec-4735-8707-5a74c2e51751

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)CagayanGattaranNabaccayan
Storms whose wind field reached it
Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025Mitag 2025
Hazard exposure
Active fault4.0 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.