Contractor Concentration (Flood Control)
A contractor holds a very large share of flood-control contract value in a district or province.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: RAMARPLUS INC FORMERLY RAMAR ENT received 25.5% (₱1.16B of ₱4.54B) of recorded flood-control contract value in Albay 3rd District Engineering Office across 53 contracts and 12 contractors, at or above the 25% share threshold (HHI 0.125). This may be because the contractor is highly competitive or specializes in flood-control projects in this area.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Flagged peer group: Albay 3rd District Engineering Office
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Agos River Control Structure, barangay La Purisima, Polangui, Albay23FO0048Flood control | 100% | May 8, 2024 | May 8, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Agos River Control Structure, barangay Lourdes, Polangui, Albay23FO0048Flood control | 100% | May 8, 2024 | May 8, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bacolod Flood Control Structure (Rightside facing Downstream of Bacolod Bridge) Bacolod, Libon, Albay23FO0053Flood control | 100% | February 26, 2024 | November 15, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Catburawan River Flood Control Structure, Barangay Catburawan, Ligao City, Albay22FO0055Flood control | 100% | March 1, 2023 | March 1, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure (Facing Downstream along River Dam Section) Zone 1, Barangay Sta. Cruz, Libon, Albay24FO0100Flood control | 100% | April 5, 2025 | April 5, 2025 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Right Side Facing Upstream of Double Barrel Box Culvert at Sitio Camlambay, Brgy. Bulusan, Libon, Albay23FO0053Flood control | 100% | February 26, 2024 | November 15, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 10 more projects in this bucket
| Construction of Flood Revetment Wall Zone 1 and 2, barangay San Agustin, Libon, Albay23FO0062Flood control | 100% | March 9, 2024 | November 30, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Kalakran River Flood Control Structure, Barangay Pistola, Oas, Albay22FO0100Flood control | 100% | May 12, 2023 | March 31, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Nagasgasan River Flood Control Structure, Barangay Obaliw Rinas, Oas, Albay22FO0100Flood control | 100% | May 12, 2023 | March 31, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Pinanganuran River Flood Control Structure, Barangay San Jose, Libon, Albay22FO0056Flood control | 100% | December 31, 2022 | December 15, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Pinanganuran River Flood Control Structure, Barangay Villa Petrona, Libon, Albay22FO0056Flood control | 100% | December 31, 2022 | December 15, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Quinale "A" River Flood Mitigation Structure (Polangui and Libon Section), Polangui, Albay22F00020Flood control | 100% | January 24, 2023 | January 24, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Bacolod Flood Control Structure (Left Side Facing Downstream of Bacolod Bridge) Phase II in Libon, Albay22FO0057Flood control | 100% | December 31, 2022 | December 16, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Left and Right Side of Talisay River Flood Mitigation Structure, Brgy. Zone 4, Libon, Albay23FO0062Flood control | 100% | March 9, 2024 | November 30, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Marocmoc Bridge Flood Control Structure (Right Side Facing Upstream and Left Side Facing Downstream of Marocmoc Bridge) in Libon, Albay22FO0057Flood control | 100% | December 31, 2022 | December 16, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Pangarian River Flood Mitigation Structure with Access Road, Barangay La Medalla, Pio Duran, Albay22FO0055Flood control | 100% | March 1, 2023 | March 1, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.
Triggering Data & citations
Contractor holds a large share of flood-control contract value in its district/province
{
"hhi": 0.1253933240192899,
"scope": "deo",
"bucketKey": "deo:Albay 3rd District Engineering Office",
"contractor": "RAMARPLUS INC FORMERLY RAMAR ENT",
"thresholds": {
"share": 0.25,
"minContracts": 3,
"minBucketContracts": 10
},
"bucketTotalPhp": 4537600835.47,
"contractorShare": 0.25503144707089137,
"contractorTotalPhp": 1157230907.3,
"contractorContracts": 16
}Source documents