Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Anomalies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24BH0194 (₱72.38M) is recorded as completed in 84 days against 264 planned; similar-cost projects take a median of 285 days, putting it in the fastest 2.6%. The contractor may have deployed unusually large resources or worked in favorable conditions, allowing for rapid completion.

Public record entityConstruction of Disimpit Flood Control Structure, Jones, Isabela
LocationJONES (ISABELA), ISABELA, Region IIContract 24BH0194
Amount₱72,375,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Disimpit Flood Control Structure, Jones, Isabela24BH0194Flood control100%February 16, 2025August 20, 2024—completedsumbong source

Start: May 28, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-05-28T00:00:00.000Z",
  "contractId": "24BH0194",
  "actualEndDate": "2024-08-20T00:00:00.000Z",
  "targetEndDate": "2025-02-15T00:00:00.000Z",
  "contractCostPhp": 72375000
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo