High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: M MONTESCLAROS ENT INC holds 30 flood-control contracts worth ₱3.16B, 3.11× the 95th-percentile contractor total (₱1.01B); up to 24 ran at the same time. This is a capacity question worth examining. Large contractors may have the resources and experience to handle many projects at once.

Public record entityM MONTESCLAROS ENT INCOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 30Ongoing: 0Delayed: 0Status unknown: 0
Show 24 more projects in this bucket
Construction of Flood Control Structure along Maramag Maradugao (Downstream), Macapantig Bridge with slope protection, Package 3, Kalilangan, Bukidnon23K00138Flood control100%June 14, 2024January 31, 2025—completedsumbong source
Construction of Flood Control Structure along Maramag Maradugao Road (Downstream), Macapantig Bridge with Slope Protection, Kalilangan, Bukidnon22KC0036Flood control100%March 4, 2023March 2, 2023—completedsumbong source
Construction of Flood Control Structure along Tigwa River, San Fernando, Bukidnon23K00108Flood control100%October 28, 2023February 1, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 1, Valencia City, Bukidnon22K00343Flood control100%June 10, 2023January 28, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 2, Valencia City, Bukidnon22K00344Flood control100%August 29, 2023March 3, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 3, Valencia City, Bukidnon22K00350Flood control100%August 29, 2023March 3, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 4, Valencia City, Bukidnon22K00348Flood control100%August 12, 2023March 3, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 5, Valencia City, Bukidnon23K00061Flood control100%December 9, 2023November 8, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 7, Valencia City, Bukidnon23K00066Flood control100%December 9, 2023May 27, 2024—completedsumbong source
Construction of Flood Control Structure with Esplanade along Valencia Bypass Road Extension, (Sugod Bridge Section), Package 8, Valencia City, Bukidnon23K00139Flood control100%January 22, 2024January 28, 2024—completedsumbong source
Construction of Flood Mitigating Structure along Pulangi River, Downstream of New Batangan Bridge, Valencia City, Bukidnon24K00052Flood control100%December 28, 2024December 28, 2024—completedsumbong source
Construction of Flood Mitigating Structure within Mindanao River Basin, along Pulangi River, Package 3, Downstream of Old Batangan Bridge, Valencia City, Bukidnon24K00107Flood control100%February 11, 2025February 6, 2025—completedsumbong source
Construction of Flood Mitigation Structure along Iponan River (Iponan Section), Cagayan de Oro City, Misamis Oriental21K00273Flood control100%December 31, 2023December 31, 2023—completedsumbong source
Construction of Flood Mitigation Structure along Kapalong-Talaingod-Valencia Road (Malambago Stream - Tributary to Pulangui River), Barangay Malambago, Package 2, San Fernando, Bukidnon23K00100Flood control100%November 5, 2023May 1, 2024—completedsumbong source
Construction of Flood Mitigation Structure along Kapalong-Talaingod-Valencia Road (Malambago Stream - Tributary to Pulangui River), Brgy. Malambago, Sta. 0+200 - Sta. 0+400 (BS), San Fernando, Bukidnon22KA0060Flood control100%September 3, 2023September 3, 2023—completedsumbong source
Construction of Flood Mitigation Structure along Kapalong-Talaingod-Valencia Road (Tigwa River), Barangay Halapitan, San Fernando, Bukidnon23KA0047Flood control100%November 11, 2023November 11, 2023—completedsumbong source
Construction of Flood Mitigation Structure along Pulangi River, Package 1, San Isidro, Valencia City, Bukidnon23K00140Flood control100%January 22, 2024April 28, 2024—completedsumbong source
Construction of Flood Mitigation Structure along Pulangi River, Package 2, San Isidro, Valencia City, Bukidnon23K00141Flood control100%January 22, 2024February 21, 2024—completedsumbong source
Construction of Flood Mitigation Structure along Sayre Highway (Malingon Creek), Barangay Bagontaas, Valencia City, Bukidnon23KA0045Flood control100%November 11, 2023November 11, 2023—completedsumbong source
Construction of Flood Mitigation Structure within Mindanao River Basin (along Pulangui River) Package 1, Downstream of Old Batangan Br., Brgy. Batangan Section, Sta. 0+000.00 - Sta. 1+535.00, Valencia City, Bukidnon22K00055Flood control100%March 18, 2023December 31, 2023—completedsumbong source
Construction of Flood Mitigation Structures within Mindanao River Basin (along Pulangui River), Downstream of New Batangan Bridge, Barangay Poblacion Section, Valencia City, Bukidnon21K00259Flood control100%November 10, 2022August 27, 2023—completedsumbong source
Construction of Flood Mitigation Structures within Mindanao River Basin (along Pulangui River), Downstream of New Batangan Bridge, Brgy. Poblacion Section, Valencia City, Bukidnon23KA0075Flood control100%January 1, 2024January 1, 2024—completedsumbong source
Construction of Flood Mitigation Structures within Mindanao River Basin (along Pulangui River), Left Side, Bukidnon21K00261Flood control100%March 22, 2022July 25, 2022—completedsumbong source
Construction of Main Drainage Canal along BCIR - JCT Rosales Avenue - LADP CARBDP Main Drainage Channel (Barangay Imadejas to Barangay Libertad) Package 1, Butuan City, Agusan del Norte22N00096100%June 13, 2023June 13, 2023—completedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "M MONTESCLAROS ENT INC",
  "projectCount": 30,
  "totalValuePhp": 3156713417.13,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name