Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22BG0005 lists a cost of ₱44.08M, 0.58% above its Approved Budget for the Contract of ₱43.83M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a late adjustment to the ABC that was not reflected in the records.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Cagayan River Flood Control Project, Brgy. Minanga, Naguilian, Isabela22BG0005Flood control | 100% | March 16, 2023 | March 16, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: February 14, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Isabela 3rd District Engineering Office",
"ratio": 1.0057656737677123,
"abcPhp": 43831597.17,
"threshold": 0.995,
"contractId": "22BG0005",
"contractor": "ARCINUE COMM'L CORP",
"contractCostPhp": 44084315.86
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to a data entry error or a late adjustment to the ABC that was not reflected in the records.
Cite this record
Love the Philippines. “Awards Very Close to the Budget Ceiling (C2): Construction of Cagayan River Flood Control Project, Brgy. Minanga, Naguilian, Isabela.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/94f1099e-f128-4bc4-b478-d40e339e7d4c
The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.