Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 4 contracts awarded to PANAY EAST COAST CONST & SUPPLY by the same office started within 19 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is possible that these are legitimate separate flood control projects in different barangays or municipalities, each requiring its own contract.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Tumagbok Flood Control Structure including Access Road, Miagao, Iloilo23GF0085Flood control | 100% | February 4, 2024 | March 1, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 31, 2023 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Iloilo 1st District Engineering Office",
"contractId": "23GF0085",
"contractor": "PANAY EAST COAST CONST & SUPPLY",
"windowDays": 120,
"clusterSize": 4,
"thresholdPhp": 50000000,
"contractCostPhp": 48489591.89,
"averageTitleSimilarity": 0.876417175840987
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program