Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24PF0020 (₱67.46M) is recorded as completed in 71 days against 294 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.7%. This could be due to unusually efficient work, favorable weather, or early completion of preparatory activities.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Mitigation Structure along Agno River, Tin-apan Section, Sta. 0+058 - Sta. 0+650 (B.S), Buguias, Benguet24PF0020Flood control | 100% | March 5, 2025 | July 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: May 15, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-05-15T00:00:00.000Z",
"contractId": "24PF0020",
"actualEndDate": "2024-07-25T00:00:00.000Z",
"targetEndDate": "2025-03-04T00:00:00.000Z",
"contractCostPhp": 67462363.43
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
- This could be due to unusually efficient work, favorable weather, or early completion of preparatory activities.
