Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24HO0083 (₱29.39M) is recorded as completed in 49 days against 200 planned; similar-cost projects take a median of 239 days, putting it in the fastest 0.8%. The project may have been completed unusually quickly due to efficient work, favorable conditions, or early completion of a partial scope.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Revetment Wall at Barangay Bala - Barangay Lanao (Upstream Right Side), Moalboal, Cebu24HO0083Flood control | 100% | September 13, 2024 | April 15, 2024 | — | completedsumbong source |
Start: February 26, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-02-26T00:00:00.000Z",
"contractId": "24HO0083",
"actualEndDate": "2024-04-15T00:00:00.000Z",
"targetEndDate": "2024-09-12T00:00:00.000Z",
"contractCostPhp": 29394904.7
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo