Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24BH0187 (₱96.50M) is recorded as completed in 70 days against 301 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.6%. The contractor may have deployed unusually large resources or worked in favorable conditions, allowing for rapid completion.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Dipangit Flood Control Structure, Section 3, Jones, Isabela24BH0187Flood control | 100% | April 10, 2025 | August 22, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 13, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-06-13T00:00:00.000Z",
"contractId": "24BH0187",
"actualEndDate": "2024-08-22T00:00:00.000Z",
"targetEndDate": "2025-04-09T00:00:00.000Z",
"contractCostPhp": 96500000
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
Cite this record
Love the Philippines. “Schedule / Date Inconsistencies (C4): Construction of Dipangit Flood Control Structure, Section 3, Jones, Isabela.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/c1d30b32-6b49-4d54-b536-09937fe5611b
The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.
