High Concurrent Workload for One Contractor
Contractor linked to many simultaneous projects or very high total value vs peers.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: NORTHERN BUILDERS holds 22 flood-control contracts worth ₱2.07B, 2.04× the 95th-percentile contractor total (₱1.01B); up to 10 ran at the same time. This is a capacity question worth examining. The contractor may have unusually high capacity or specialization in flood-control projects.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Brgy. Aplaya Seawall, Bongabong, Oriental Mindoro21EI0150Flood control | 100% | October 31, 2022 | October 24, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Naawan River Upstream of Naawan Bridge (Right side), Package 3, Naawan, Misamis Oriental22K00226Flood control | 100% | July 8, 2023 | July 8, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Naawan River Upstream of Naawan Bridge (Right side), Package 4, Naawan, Misamis Oriental22K00227Flood control | 100% | July 8, 2023 | July 8, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Tagabaca-Aupagan, Phase 1, Butuan City22ND0057Flood control | 100% | May 29, 2023 | May 12, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Flood Control Works - Construction of Guagua Pasac River23C00054Flood control | 100% | May 26, 2024 | November 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Existing Dike along Rio Chico River (Lara Section, Right Bank), Package 1, La Paz, Tarlac (Sta. 0+819 to Sta. 1+313)23CK0063Flood control | 100% | December 23, 2023 | September 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 16 more projects in this bucket
Rule Definition
Active project count and total value vs peer 95th percentile.
Triggering Data & citations
Contractor carries far more concurrent flood-control value than peers
{
"contractor": "NORTHERN BUILDERS",
"projectCount": 22,
"totalValuePhp": 2068794385.94,
"peerP95TotalPhp": 1014143494.4100002,
"activeProjectCount": 0,
"simultaneousThreshold": 25
}Source documents
Possible Innocent Explanations
- Large national firm with many concurrent government clients
- Data groups joint ventures under one name