Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22HK0044 was awarded at 100.00% of its ABC. Across its 88 recorded contracts, QM BUILDERS was awarded at ≥99.5% of ABC 84 times (95.5%), versus 70.4% for flood-control contracts overall. It is possible that the winning bid simply matched the ABC exactly, which is allowed under procurement rules.

Public record entityReconstruction of Tugas-Polo Seawall, Tanjay City, Negros Oriental
LocationCITY OF TANJAY (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VIIContract 22HK0044
Amount₱67,550,000.00100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Reconstruction of Tugas-Polo Seawall, Tanjay City, Negros Oriental22HK0044Flood control100%November 9, 2022November 9, 2022—completedsumbong source

Start: February 18, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Negros Oriental 2nd District Engineering Office",
  "ratio": 1,
  "abcPhp": 67550000,
  "threshold": 0.995,
  "contractId": "22HK0044",
  "contractor": "QM BUILDERS",
  "contractCostPhp": 67550000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate