Love the Philippines

Anomaly / indicator worth examining β€” not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin β€” hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

Bid-Ceiling Hugging

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining β€” not proof of wrongdoing, fraud, or corruption against any person.

Indicator: Quezon 2nd District Engineering Office awarded 35 of 35 recorded flood-control contracts (100.0%) at 99.5% or more of their Approved Budget for the Contract, versus 70.4% for flood-control contracts nationwide (29.6 percentage points higher; binomial p = 4.6e-06), across 10 contractors. Source: DPWH / Sumbong sa Pangulo contract records; each contract is listed below. This pattern may result from consistently competitive bidding or careful cost estimation.

Public record entityData not yet available
Locationβ€”
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Quezon 2nd District Engineering Office: contracts

35 of 35 contracts (100%) at β‰₯99.5% of ABC Β· peer baseline 70.4% Β· gap +29.6 pts Β· binomial p = 4.6e-6. Source: DPWH transparency portal and Sumbong sa Pangulo records (linked per contract).

ContractTitleContractor% of ABCSource
23DJ0022Construction of Balubal River Flood Control, Sariaya, QuezonI A BOSQUE CONST CORP100.00%DPWH
22DJ0126Construction of Slope Protection along Lagnas River (Downstream - Package 2), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
22DJ0128Construction of Slope Protection along Lagnas River (Downstream - Package 3), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
22DJ0147Construction of Dumacaa River Flood Control, Brgy. Cotta, Lucena City, Quezon (Package 3)RAPID FOREMOST CONST CO100.00%DPWH
22DJ0073Construction of Slope Protection along Dumacaa River, Barangay IX, Lucena City, QuezonI A BOSQUE CONST CORP100.00%DPWH
22DJ0131Construction of Slope Protection along Lagnas River (Upstream - Package 5), Sariaya, QuezonI A BOSQUE CONST CORP100.00%DPWH
22DJ0125Construction of Slope Protection along Lagnas River (Upstream - Package 2), Sariaya, QuezonRAPID FOREMOST CONST CO / JAICA CONST CORP100.00%DPWH
22DJ0027Construction of Slope Protection along Lagnas River, Barangay Sampaloc II, Sariaya, QuezonI A BOSQUE CONST CORP100.00%DPWH
22DJ0135Construction of Slope Protection along Lagnas River (Upstream - Package 7), Sariaya, QuezonRAPID FOREMOST CONST CO100.00%DPWH
22DJ0133Construction of Slope Protection along Lagnas River (Upstream - Package 6), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY / ROMHEAD S J BUILDERS AND DEVELOPMENT INC100.00%DPWH
22DJ0132Construction of Slope Protection along Lagnas River (Downstream - Package 5), Sariaya, QuezonI A BOSQUE CONST CORP100.00%DPWH
22DJ0064Construction of Dumacaa River Flood Control, Brgy. Cotta, Lucena City, QuezonRAPID FOREMOST CONST CO / JAICA CONST CORP100.00%DPWH
22DJ0130Construction of Slope Protection along Lagnas River (Downstream - Package 4), Sariaya, QuezonJEMAK CONST & SUPPLY / FREPA BUILDER AND CONST SUPPLY100.00%DPWH
21DJ0079Construction of River Control, Brgy. 11, Lucena CityRAPID FOREMOST CONST CO / WYDERWAYS BUILDERS AND SUPPLIES100.00%DPWH
22DJ0016Construction of Slope Protection along Dumuklong River, Barangay Kanlurang Mayao, Lucena City, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
22DJ0110Construction of Flood Control and Drainage Structure, Barangay Poblacion 9, Lucena City, QuezonJAICA CONST CORP100.00%DPWH
22DJ0066Construction of Slope Protection along Lagnas River (Upstream - Package 1), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
22DJ0148Construction of Box Culvert, Brgy. Domoit, Lucena City, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
22DJ0136Construction of Slope Protection along Lagnas River (Downstream - Package 7), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY / ROMHEAD S J BUILDERS AND DEVELOPMENT INC100.00%DPWH
22DJ0049Construction of Slope Protection along Quiapo River, Barangay Pahinga Norte to Barangay Poblacion, Candelaria, QuezonI A BOSQUE CONST CORP100.00%DPWH
23DJ0101Construction of Morong River Flood Control (Package 12), Sariaya, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY100.00%DPWH
21DJ0052Construction of Slope Protection along Dumacaa River, Brgy. 10, Lucena City, QuezonRAPID FOREMOST CONST CO100.00%DPWH
22DJ0149Construction of Dumacaa River Flood Control, Brgy. Cotta, Lucena City, Quezon (Package 2)RAPID FOREMOST CONST CO100.00%DPWH
24DJ0115Construction of Dumacaa River Flood Control Structure (Package 22), Lucena City, QuezonUNIVERSAL DE LEON CONST AND AGGREGATES100.00%DPWH
24DJ0039Construction of Flood Control (Riprap), KMNAI, Barangay Kanlurang Mayao, Lucena City, QuezonJAICA CONST CORP100.00%DPWH
22DJ0109Construction of Dumacaa River Flood Control, Brgy. 2, Lucena City, QuezonJAICA CONST CORP100.00%DPWH
22DJ0129Construction of Slope Protection along Lagnas River (Upstream - Package 4), Sariaya, QuezonI A BOSQUE CONST CORP100.00%DPWH
21DJ0057Construction of River Control, Brgy. Cotta (Phase II), Lucena CityRAPID FOREMOST CONST CO100.00%DPWH
22DJ0001Construction of Slope Protection along Quiapo River, Brgy. Pahinga Norte to Brgy. Poblacion, Candelaria, QuezonRAPID FOREMOST CONST CO100.00%DPWH
23DJ0073Construction of Dumacaa River Flood Control (Package 8), Lucena City, QuezonRAPID FOREMOST CONST CO / JELCON-CONST AND TRADING CORP100.00%DPWH
23DJ0016Construction of Iyam River Flood Control (Package 1), Lucena City, QuezonRAPID FOREMOST CONST CO100.00%DPWH
22DJ0071Construction of Iyam River Flood Control, Brgy. Cotta (Phase 3), Lucena City, QuezonRAPID FOREMOST CONST CO / JAICA CONST CORP100.00%DPWH
23DJ0072Construction of Dumacaa River Flood Control (Package 9), Lucena City, QuezonRAPID FOREMOST CONST CO100.00%DPWH
23DJ0094Construction of Seawall, Barangay Barra, Lucena City, QuezonWAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS & CONST SUPPLY / ROMHEAD S J BUILDERS AND DEVELOPMENT INC100.00%DPWH
23DJ0080Construction of Seawall, Barangay Talao-Talao, Lucena City, QuezonI A BOSQUE CONST CORP100.00%DPWH

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list β€” not inferred beyond those columns.

Completion schedule is shown for project and contractor flags only.

Rule Definition

ContractCost / ABC β‰₯ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Implementing office awards near-ABC contracts far more often than the flood-control baseline

{
  "office": "Quezon 2nd District Engineering Office",
  "nearAbc": 35,
  "trigger": "office_pattern_aggregate",
  "officeId": "0ddc7b85-d00e-5810-ac15-545cb32d9625",
  "threshold": 0.995,
  "binomialTailP": 0.000004626135414973895,
  "nearAbcRatePct": 100,
  "totalContracts": 35,
  "baselineRatePct": 70.4,
  "excessPctPoints": 29.6,
  "expectedNearAbc": 24.6,
  "baselineDefinition": "share of all Sumbong flood-control contracts awarded at β‰₯99.5% of ABC"
}

Possible Innocent Explanations

Data not yet available (source: rule metadata)