Construction of Flood Mitigation Structure24DJ0039

Construction of Flood Control (Riprap), KMNAI, Barangay Kanlurang Mayao, Lucena City, Quezon

Construction of Flood Control (Riprap), KMNAI, Barangay Kanlurang Mayao, Lucena City, Quezon is a DPWH-tracked public work in LUCENA CITY (CAPITAL) (QUEZON), QUEZON, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: JAICA CONST CORP. Figures trace to sumbong.

LUCENA CITY (CAPITAL) (QUEZON), QUEZON, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control ( Riprap ) , KMNAI, Barangay Kanlurang Mayao, Lucena City, Quezon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004414

₱1,010,550.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008428

₱1,394,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004490

₱82,404.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008429

₱129,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0017822

₱1,159,874.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24DJ0039

₱4,900,561.18 · JAICA CONST. .

Contractor

C

169 projects · ₱2.3B total · 0 flags

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2024

Target End

July 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.