Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24HC0057 lists a cost of ₱39.57M, 0.93% above its Approved Budget for the Contract of ₱39.20M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a post-award adjustment not reflected in the ABC.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Ubay Flood Control Structure, Barangay Bongbong-Barangay San Pascual, Ubay, Bohol24HC0057Flood control | 100% | May 8, 2025 | April 15, 2025 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: May 9, 2024 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Bohol 2nd District Engineering Office",
"ratio": 1.0093270214285714,
"abcPhp": 39200000,
"threshold": 0.995,
"contractId": "24HC0057",
"contractor": "ZLREJ TRADING AND CONST CORP",
"contractCostPhp": 39565619.24
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to a data entry error or a post-award adjustment not reflected in the ABC.