Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23HN0056 was awarded at 99.97% of its ABC. Across its 32 recorded contracts, QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST was awarded at ≥99.5% of ABC 31 times (96.9%), versus 70.4% for flood-control contracts overall. Contractors may consistently bid close to the ABC to maximize their chances of winning while staying within legal limits.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Basak Creek, Mandaue City, Cebu23HN0056Flood control | 100% | January 7, 2024 | January 7, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: May 12, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Cebu 6th District Engineering Office",
"ratio": 0.9996915918367347,
"abcPhp": 49000000,
"threshold": 0.995,
"contractId": "23HN0056",
"contractor": "QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST",
"contractCostPhp": 48984888
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
