Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24HN0024 was awarded at 99.90% of its ABC. Across its 32 recorded contracts, QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST was awarded at ≥99.5% of ABC 31 times (96.9%), versus 70.4% for flood-control contracts overall. Contractors may consistently bid close to the ABC to remain competitive while maximizing their potential profit.

Public record entityConstruction of Flood Control Structure along Cansaga River, Barangay Garing, Phase 3, Consolacion, Cebu
LocationCONSOLACION (CEBU), CEBU, Region VIIContract 24HN0024
Amount₱96,399,888.0099.90% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Cansaga River, Barangay Garing, Phase 3, Consolacion, Cebu24HN0024Flood control100%August 11, 2024August 9, 2024—completedsumbong source

Start: February 16, 2024 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Cebu 6th District Engineering Office",
  "ratio": 0.9989625699481866,
  "abcPhp": 96500000,
  "threshold": 0.995,
  "contractId": "24HN0024",
  "contractor": "QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST",
  "contractCostPhp": 96399888
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate