Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24BI0039 (₱49.00M) is recorded as completed in 43 days against 229 planned; similar-cost projects take a median of 239 days, putting it in the fastest 0.6%. The project may have been completed quickly due to favorable weather, efficient contractor performance, or prior preparatory work.

Public record entityConstruction of Manamtam Floos Control along Matuno River (Section 2), Bambang, Nueva Vizcaya
LocationBAMBANG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region IIContract 24BI0039
Amount₱49,000,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Manamtam Floos Control along Matuno River (Section 2), Bambang, Nueva Vizcaya24BI0039Flood control100%September 29, 2024March 27, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 13, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-02-13T00:00:00.000Z",
  "contractId": "24BI0039",
  "actualEndDate": "2024-03-27T00:00:00.000Z",
  "targetEndDate": "2024-09-28T00:00:00.000Z",
  "contractCostPhp": 49000000
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)Nueva VizcayaBambangManamtam
Storms whose wind field reached it
Peilou 2026Fung-Wong 2025Fengshen 2025Matmo 2025Mitag 2025
Hazard exposure
Active fault7.5 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgeno layer coverage for this provinceUP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.