Bid-Ceiling Hugging
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22BE0023 was awarded at 99.66% of its ABC. Across its 37 recorded contracts, EGB CONST CORP FORMERLY: EGB CONST was awarded at ≥99.5% of ABC 36 times (97.3%), versus 70.4% for flood-control contracts overall. This pattern may result from consistently competitive bidding or precise cost estimation.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Barangay Fugu Sur to Fugu Norte Flood Control System, Phase II, Tumauini, Isabela22BE0023Flood control | 100% | October 3, 2022 | September 9, 2022 | — | completedsumbong source |
Start: February 15, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Isabela 1st District Engineering Office",
"ratio": 0.9965986333333333,
"abcPhp": 29400000,
"threshold": 0.995,
"contractId": "22BE0023",
"contractor": "EGB CONST CORP FORMERLY: EGB CONST",
"contractCostPhp": 29299999.82
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate