Roads24HG0069

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF BARANGAY EL PARDO-BARANGAY NANGKA ROAD, BOLJOON, CEB

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF BARANGAY EL PARDO-BARANGAY NANGKA ROAD, BOLJOON, CEB is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱4,940,000.00. Status: Reported complete (DPWH). Contractor on record: WYNE ROSE CONST AND SUPPLY CORP. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bulacao River Flood Control Structure, Talisay City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0004574

₱2,383,785.00 · FY2024

Released to Regional Office - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

26 projects · ₱564.6M total · 0 flags

4. Implementation

Contract Amount

₱4,940,000.00

Progress

Reported complete (DPWH)

Start Date

May 15, 2024

Target End

June 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.