Flood Control and Drainage24CC0665

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY MANATAL (PUROK 3 TO PUROK 5), PANDI, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY MANATAL (PUROK 3 TO PUROK 5), PANDI, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱46,459,863.05. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱46,459,863.05

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 28, 2025

Target End

October 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.