Construction of Flood Mitigation Structure24CC0170

Construction of Reinforced Concrete Flood Control Structure at Barangay San Roque (Purok 3 to Purok 5), Baliuag, Bulacan

Construction of Reinforced Concrete Flood Control Structure at Barangay San Roque (Purok 3 to Purok 5), Baliuag, Bulacan is a DPWH-tracked public work in CITY OF BALIUAG (BULACAN), BULACAN, Region III. Reported contract value: ₱77,199,677.98. Status: Reported complete (DPWH). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to sumbong.

CITY OF BALIUAG (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0017122

₱99,000.00 · FY2024

Released to Banga National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

161 projects · ₱8.0B total · 11 flags

4. Implementation

Contract Amount

₱77,199,677.98

Progress

Reported complete (DPWH)

Start Date

February 28, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.