Flood Control and Drainage18DO0101

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG UPPER MARIKINA RIVER, SAN MATEO

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG UPPER MARIKINA RIVER, SAN MATEO is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱28,224,321.09. Status: Reported complete (DPWH). Contractor on record: DAHL CONST CORP FORMERLY: DAHL CONST. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Upper Marikina River, San Mateo, Rizal
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-18-0010660

₱66,549.00 · FY2018

Released to Davao del Sur District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

148 projects · ₱4.8B total · 1 flags

4. Implementation

Contract Amount

₱28,224,321.09

Progress

Reported complete (DPWH)

Start Date

June 7, 2018

Target End

October 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.