Construction of Flood Mitigation Structure23OE0086

Construction of Reinforced Concrete Box Culvert (RCBC) along Geronimo Street, Manila City

Construction of Reinforced Concrete Box Culvert (RCBC) along Geronimo Street, Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱54,088,655.12. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱40,343,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Easement Road Estero de Pandacan (Tripa de Gallina - P. Quirino Ave.) Manila
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-23-0023041

₱86,456.00 · FY2023

Released to Cotabato State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱54,088,655.12

Progress

Reported complete (DPWH)

Start Date

March 15, 2023

Target End

March 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.