Roads24HN0073

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM -PREVENTIVE MAINTENANCE - SECONDARY ROADS - UN AVENUE (CB) - CHAINAGE 0 - CHAINAGE 900, CHAINAGE 7 - CHAINAGE 220, CHAINAGE 2037 - CHAINAGE 2250, MANDAUE CITY, CEBU

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM -PREVENTIVE MAINTENANCE - SECONDARY ROADS - UN AVENUE (CB) - CHAINAGE 0 - CHAINAGE 900, CHAINAGE 7 - CHAINAGE 220, CHAINAGE 2037 - CHAINAGE 2250, MANDAUE CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱25,480,000.00. Status: Reported complete (DPWH). Contractor on record: A S T BUILDERS. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Gate at Basak Creek, Lapu - Lapu City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

36 projects · ₱920.2M total · 0 flags

Other projects by this contractor

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MANANGA RIVER, BARAN

Cebu City DEO, Region VII

2024₱96.4M
Reported complete (100% progress, DPWH status On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MANANGA RIVER, BARAN

Cebu City DEO, Region VII

2024₱96.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-PRIMARY ROADS-CEBU NORTH RD-(S00321CB) CHAINAGE 000-CHAINAGE 696, (S00016CB) K0001+(-048)-K0001+653, (S00017CB) K0003+(-1339)-K0003+(-839), CEBU CITY

Cebu City DEO, Region VII

2023₱91.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-CEBU BALAMBAN TRANSCENTRAL HIGHWAY - K0027+254 -K0027+475, CEBU CITY

Cebu City DEO, Region VII

2023₱71.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS - CEBU BALAMBAN TRANSCENTRAL HIGHWAY- K0025+134 - K0025+267, CEBU CITY

Cebu City DEO, Region VII

2023₱60.8M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Cansag River, Brgy Danglag (Phase IV), Consolacion, Cebu

CONSOLACION (CEBU), CEBU, Region VII

2022₱49.5M
Reported complete (DPWH)
View all 36 projects →

4. Implementation

Contract Amount

₱25,480,000.00

Progress

Reported complete (DPWH)

Start Date

February 23, 2024

Target End

April 11, 2024

5. Audit