GAA 2025 SSP25PB0035

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), KARIKITAN, CONNER, APAYAO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), KARIKITAN, CONNER, APAYAO is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱7,741,660.91. Status: Past target date (DPWH On-Going). Contractor on record: ENRIQUE T CHUA CONST DEVELOPMENT CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱12,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIVB-25-0010863 · ₱509,667 · release to the district office, not itemized per project

    Possible match · score 0.59

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25PB0035 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    81% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), KARIKITAN, CONNER, APAYAO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barren River Flood Control Structure along Chico River Basin, Conner, Apayao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-25-0010863

₱509,667.00 · FY2025

Released to Tigwi National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱387.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱117.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONBAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD.(BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ)-CHAINAGE 0- CHAINAGE 3900

Apayao 1st DEO, Cordillera Administrative Region

2025₱60.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD (BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ) - CHAINAGE 8158 - CHAINAGE

Apayao 1st DEO, Cordillera Administrative Region

2025₱52.0M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO - CONSTRUCTION OF CONCRETE BRIDGE

Apayao 1st DEO, Cordillera Administrative Region

2020₱49.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (APAYAO TOURISM BUILDING), LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2023₱29.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA- KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 2, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱28.8M
Reported complete (100% progress, DPWH status On-Going)
View all 10 projects →

4. Implementation

Contract Amount

₱7,741,660.91

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

January 13, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.