Roads25HE0001

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO MALALAG, BAR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO MALALAG, BAR is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱14,670,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: WYNE ROSE CONST AND SUPPLY CORP. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Mananga River (Right Side) at Sitio Cambawog (Upper), Camp IV, Talisay City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

26 projects · ₱564.6M total · 0 flags

4. Implementation

Contract Amount

₱14,670,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 13, 2025

Target End

May 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.