Roads20CC0113

OFF CARRIAGEWAY IMPROVEMENT - PRIMARY ROAD - DAANG MAHARLIKA (LZ) K0040+171, K0040+455, K0040+825, K0041+800, K0050+880, PLARIDEL & BALIUAG, BULACAN

OFF CARRIAGEWAY IMPROVEMENT - PRIMARY ROAD - DAANG MAHARLIKA (LZ) K0040+171, K0040+455, K0040+825, K0041+800, K0050+880, PLARIDEL & BALIUAG, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱32,064,911.71. Status: Reported complete (DPWH). Contractor on record: A R L CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱48,594 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱30,782,265 · ARL CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-06-26 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OFF CARRIAGEWAY IMPROVEMENT - PRIMARY ROAD - DAANG MAHARLIKA (LZ) K0040+171, K0040+455, K0040+825, K0041+800, K0050+880, PLARIDEL & BALIUAG, BULACAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱48,594,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Angat River, Makinabang Section, Sta. 00+000 to Sta. 00+353.60, Baliuag, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱32,064,911.71

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

October 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.