Flood Control and Drainage24CC0624

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (WATER INTERCEPTOR) ALONG MANILA NORTH ROAD, PHASE 1, BULIHAN LONGOS SECTION, MALOLOS, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (WATER INTERCEPTOR) ALONG MANILA NORTH ROAD, PHASE 1, BULIHAN LONGOS SECTION, MALOLOS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱138,957,268.65. Status: Past target date (DPWH On-Going). Contractor on record: A R L CONST 27645. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱138,957,268.65

Progress

Past target date (DPWH On-Going)

Start Date

January 6, 2025

Target End

November 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.