Buildings and Facilities17EF0105No coordinates published by DPWH

CONST. OF CLASSROOM: BULNO PS 1STY2CL, RIZAL (MARCOS), PALAWAN

CONST. OF CLASSROOM: BULNO PS 1STY2CL, RIZAL (MARCOS), PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱2,614,480.83. Status: Reported complete (DPWH). Contractor on record: CRISHELLE CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-B

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱15,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-17-0003602 · ₱84,758 · release to the district office, not itemized per project

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17EF0105 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱1,307,240 per classroom= 1.0x the Region IV-B median (n=302)

Contract cost ₱2,614,481 ÷ 2 classroom read from the DPWH title (“1STY2CL”; classroom count in title). National percentile: 23. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONST. OF CLASSROOM: BULNO PS 1STY2CL, RIZAL (MARCOS), PALAWAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Inogbong Flood Control, Bataraza, Palawan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0003602

₱84,758.00 · FY2017

Released to Antipolo National High School, Minalabac (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

69 projects · ₱502.4M total · 0 flags

4. Implementation

Contract Amount

₱2,614,480.83

Progress

Reported complete (DPWH)

Start Date

January 11, 2018

Target End

April 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.