Buildings and Facilities19PD0091

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF COVERED COURT, PUROK 3, GIBRALTAR, BAGUIO CITY, BENGUET

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF COVERED COURT, PUROK 3, GIBRALTAR, BAGUIO CITY, BENGUET is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱3,718,038.41. Status: Reported complete (DPWH). Contractor on record: 4RMCONSTRUCTION. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0026253

₱61,610.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

17 projects · ₱174.1M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM-PAVING OF UNPAVED ROADS-TERTIARY ROADS JCT. TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD ROAD. CHAINAGE 4,685-CHAINAGE 5,275

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱22.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 3415 - CHAINAGE 4015

Mountain Province 2nd DEO, Cordillera Administrative Region

2022₱21.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-PAVING OF UNPAVED ROADS - TERTIARY ROADS, JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 4015 - CHAINAGE 4685

Mountain Province 2nd DEO, Cordillera Administrative Region

2021₱19.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, MT. PROVINCE SECTION, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2020₱19.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SPECIFIC LOCATION ALONG CITY LIMIT - STO. TOMAS ROAD (S00404LZ), K0262+532 - K0263+412, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱16.2M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY RDS, AGOO-BAGUIO CITY RD, K0240+934-K0241+234, TUBAO, LU

La Union 2nd DEO, Region I

2023₱14.5M
Reported complete (DPWH)
View all 17 projects →

4. Implementation

Contract Amount

₱3,718,038.41

Progress

Reported complete (DPWH)

Start Date

July 18, 2019

Target End

March 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.