Flood Control and Drainage23CL0053

CONSTRUCTION OF FLOOD CONTROL AT LAUIS RIVER, PHASE IV, CANDELARIA, ZAMBALES

CONSTRUCTION OF FLOOD CONTROL AT LAUIS RIVER, PHASE IV, CANDELARIA, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱94,584,467.06. Status: Past target date (DPWH On-Going). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Bucao River North Approach Downstream Phase 2, Botolan, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

217 projects · ₱8.6B total · 22 flags

Other projects by this contractor

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Mulawin, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱236.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
View all 217 projects →

4. Implementation

Contract Amount

₱94,584,467.06

Progress

Past target date (DPWH On-Going)

Start Date

March 28, 2023

Target End

February 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.