Flood Control and Drainage24CC0643

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY PRITIL (KABILANG BAKOOD TO PUROK 4) GUIGUINTO, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY PRITIL (KABILANG BAKOOD TO PUROK 4) GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱70,404,878.17. Status: Past target date (DPWH On-Going). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24CC0643 - Construction of Flood Control Structure

₱70,404,878.17 · TOPNOTCH CATALYST BUILDERS .

Confirmed (exact contract ID) · 100%

24CC0643 - Construction of Flood Control Structure

₱70,404,878.17 · TOPNOTCH CATALYST BUILDERS .

Contractor

D

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱70,404,878.17

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

October 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.