Flood Control and Drainage20LB0239

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG DAVAO RIVER, DAVAO RIVER BRIDGE UPSTREAM SECTION, RIGHT BANK, DAVAO CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG DAVAO RIVER, DAVAO RIVER BRIDGE UPSTREAM SECTION, RIGHT BANK, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: ABU CONST. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Davao River, Davao River Bridge Upstream Section, Right Bank, Davao City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Davao City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

December 16, 2020

Target End

August 1, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.