Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24CC0195 (₱67.55M) is recorded as completed in 54 days against 239 planned; similar-cost projects take a median of 285 days, putting it in the fastest 0.7%. The project may have benefited from unusually efficient work, pre-fabrication, or an overestimated planned duration.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Reinforced Concrete Flood Control Structure, Barangay Santa Monica (Purok 6 to Purok 7), Hagonoy, Bulacan24CC0195Flood control | 100% | December 13, 2024 | June 11, 2024 | — | completedsumbong source |
Start: April 18, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-04-18T00:00:00.000Z",
"contractId": "24CC0195",
"actualEndDate": "2024-06-11T00:00:00.000Z",
"targetEndDate": "2024-12-12T00:00:00.000Z",
"contractCostPhp": 67549830.35
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo