Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24AE0022 (₱82.97M) is recorded as completed in 75 days against 310 planned; similar-cost projects take a median of 285 days, putting it in the fastest 2.0%. The project may have benefited from unusually favorable conditions, such as efficient management, pre-existing site preparation, or a smaller actual scope than typical for the contract value.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Mitigation Structure along Barangay Napaset, Luna, La Union24AE0022Flood control | 100% | December 20, 2024 | April 29, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: February 14, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-02-14T00:00:00.000Z",
"contractId": "24AE0022",
"actualEndDate": "2024-04-29T00:00:00.000Z",
"targetEndDate": "2024-12-19T00:00:00.000Z",
"contractCostPhp": 82971637.15
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo