Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23E00197 was awarded at 100.00% of its ABC. Across its 115 recorded contracts, LEGACY CONST CORP FORMERLY: LEGACY CONST was awarded at ≥99.5% of ABC 100 times (87.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids at or just below the ABC to maximize their chances of winning within legal limits.

Public record entityConstruction of Mayha - Rizal Flood Control Structure, Tablas Island Romblon
LocationALCANTARA (ROMBLON), ROMBLON, Region IV-BContract 23E00197
Amount₱192,991,021.80100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Mayha - Rizal Flood Control Structure, Tablas Island Romblon23E00197Flood control100%March 22, 2024December 10, 2023—completedsumbong source

Start: March 29, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Romblon District Engineering Office",
  "ratio": 0.9999534808290156,
  "abcPhp": 193000000,
  "threshold": 0.995,
  "contractId": "23E00197",
  "contractor": "LEGACY CONST CORP FORMERLY: LEGACY CONST",
  "contractCostPhp": 192991021.8
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate