Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 22GB0014 and 23GB0023 have near-identical descriptions about 790 m apart (funding years 2022, 2023; ₱8.26M, ₱57.90M). Worth checking whether they cover the same works. It is possible that the second project is a continuation or extension of the first, or covers a different segment of the same river in the same barangay.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Sibalom River, Barangay Pantao, San Jose, Antique22GB0014Flood control | 100% | December 20, 2022 | April 22, 2023 | — | completedsumbong source |
Start: February 18, 2022 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "22GB0014",
"fundingYear": 2022,
"municipality": "SAN JOSE (CAPITAL) (ANTIQUE)",
"distanceMeters": 789.9852728635198,
"titleSimilarity": 1
}Source documents
Possible Innocent Explanations
- Phased construction seasons
- Upstream/downstream segments recorded separately