Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 24N00126 and 24N00121 have near-identical descriptions about 68 m apart (funding year 2024; ₱99.00M, ₱48.25M). Worth checking whether they cover the same works. These could be adjacent or sequential segments of shore protection funded separately in the same year.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Shore Protection Structure along Poblacion 2, Burgos, Surigao del Norte24N00126Flood control | 100% | December 28, 2024 | December 22, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: May 13, 2024 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "24N00126",
"fundingYear": 2024,
"municipality": "BURGOS (SURIGAO DEL NORTE)",
"distanceMeters": 68.38547399721955,
"titleSimilarity": 0.9433919562519968
}Source documents
Possible Innocent Explanations
- Phased construction seasons
- Upstream/downstream segments recorded separately