Bid-Ceiling Hugging
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24GK0186 was awarded at 100.00% of its ABC. Across its 115 recorded contracts, LEGACY CONST CORP FORMERLY: LEGACY CONST was awarded at ≥99.5% of ABC 100 times (87.0%), versus 70.4% for flood-control contracts overall. This could be due to highly competitive bidding or precise cost estimation.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control System, Brgy Alicante, Enrique B. Magalona, Negros Occidental24GK0186Flood control | 100% | October 13, 2024 | October 13, 2024 | — | completedsumbong source |
Start: March 13, 2024 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Negros Occidental 1st District Engineering Office",
"ratio": 0.9999548006032116,
"abcPhp": 49499996.88,
"threshold": 0.995,
"contractId": "24GK0186",
"contractor": "LEGACY CONST CORP FORMERLY: LEGACY CONST",
"contractCostPhp": 49497759.51
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
