Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Bid-Ceiling Hugging

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24GK0186 was awarded at 100.00% of its ABC. Across its 115 recorded contracts, LEGACY CONST CORP FORMERLY: LEGACY CONST was awarded at ≥99.5% of ABC 100 times (87.0%), versus 70.4% for flood-control contracts overall. This could be due to highly competitive bidding or precise cost estimation.

Public record entityConstruction of Flood Control System, Brgy Alicante, Enrique B. Magalona, Negros Occidental
LocationENRIQUE B. MAGALONA (SARAVIA) (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VIContract 24GK0186
Amount₱49,497,759.51100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control System, Brgy Alicante, Enrique B. Magalona, Negros Occidental24GK0186Flood control100%October 13, 2024October 13, 2024—completedsumbong source

Start: March 13, 2024 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Negros Occidental 1st District Engineering Office",
  "ratio": 0.9999548006032116,
  "abcPhp": 49499996.88,
  "threshold": 0.995,
  "contractId": "24GK0186",
  "contractor": "LEGACY CONST CORP FORMERLY: LEGACY CONST",
  "contractCostPhp": 49497759.51
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate