Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24CC0394 was awarded at 99.99% of its ABC. Across its 14 recorded contracts, SYMS CONST TRADING was awarded at ≥99.5% of ABC 14 times (100.0%), versus 70.4% for flood-control contracts overall. This pattern may result from consistently competitive bidding or precise cost estimation.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Reinforced Concrete Flood Control Structure, Barangay Caliligawan, Malolos City, Bulacan24CC0394Flood control | 100% | December 18, 2024 | June 24, 2024 | — | completedsumbong source |
Start: April 23, 2024 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Bulacan 1st District Engineering Office",
"ratio": 0.9998834980610961,
"abcPhp": 72374675.3,
"threshold": 0.995,
"contractId": "24CC0394",
"contractor": "SYMS CONST TRADING",
"contractCostPhp": 72366243.51
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate