Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24CM0025 (₱96.50M) is recorded as completed in 100 days against 314 planned; similar-cost projects take a median of 285 days, putting it in the fastest 4.0%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.

Public record entityImprovement of Calapacuan River, Subic, Zambales
LocationSUBIC (ZAMBALES), ZAMBALES, Region IIIContract 24CM0025
Amount₱96,499,707.06 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Improvement of Calapacuan River, Subic, Zambales24CM0025Flood control100%December 24, 2024May 24, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 14, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-02-14T00:00:00.000Z",
  "contractId": "24CM0025",
  "actualEndDate": "2024-05-24T00:00:00.000Z",
  "targetEndDate": "2024-12-23T00:00:00.000Z",
  "contractCostPhp": 96499707.06
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)ZambalesSubicCalapacuan
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
Active fault36.1 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)mediumUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgeinundated from SSA1 (2.01-3 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.