Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24A00280 (₱154.40M) is recorded as completed in 45 days against 269 planned; similar-cost projects take a median of 377 days, putting it in the fastest 0.1%. It is possible that the project was already partially completed before the official start date, or that the recorded completion date reflects only administrative closure.

Public record entityConstruction of Flood Control Structure along Baroro River, Barangay Poblacion, San Gabriel, La Union
LocationSAN GABRIEL (LA UNION), LA UNION, Region IContract 24A00280
Amount₱154,399,995.60 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Baroro River, Barangay Poblacion, San Gabriel, La Union24A00280Flood control100%November 25, 2024April 15, 2024—completedsumbong source

Start: March 1, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-03-01T00:00:00.000Z",
  "contractId": "24A00280",
  "actualEndDate": "2024-04-15T00:00:00.000Z",
  "targetEndDate": "2024-11-24T00:00:00.000Z",
  "contractCostPhp": 154399995.6
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo