Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24A00280 (₱154.40M) is recorded as completed in 45 days against 269 planned; similar-cost projects take a median of 377 days, putting it in the fastest 0.1%. It is possible that the project was already partially completed before the official start date, or that the recorded completion date reflects only administrative closure.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Baroro River, Barangay Poblacion, San Gabriel, La Union24A00280Flood control | 100% | November 25, 2024 | April 15, 2024 | — | completedsumbong source |
Start: March 1, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-03-01T00:00:00.000Z",
"contractId": "24A00280",
"actualEndDate": "2024-04-15T00:00:00.000Z",
"targetEndDate": "2024-11-24T00:00:00.000Z",
"contractCostPhp": 154399995.6
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo