Bridges18MH0053

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, COLUBI BR.1 (B00400MN) ALONG AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI ROAD PALIMBANG, SULTAN KUDARAT

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, COLUBI BR.1 (B00400MN) ALONG AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI ROAD PALIMBANG, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱9,525,482.94. Status: Reported complete (DPWH). Contractor on record: ABU CONST. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Seawall Protection, Brgy Baranayan, Palimbang, Sultan Kudarat
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-18-0004078

₱54,219.00 · FY2018

Released to Caduha-an National High re School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,525,482.94

Progress

Reported complete (DPWH)

Start Date

April 12, 2018

Target End

October 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.