Water Provision and Storage23FN0095

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS- WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM, NABUA, CAMARINES SUR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS- WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM, NABUA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: RAMARPLUS INC FORMERLY RAMAR ENT. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱9,651,503 · RAMARPLUS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-06-02 → 2025-05-31

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS- WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM, NABUA, CAMARINES SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure (Along Bicol River), Barangay Taban, Minalabac, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Camarines Sur 5th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23FN0095

₱9,651,502.73 · RAMARPLUS

Contractor

B

82 projects · ₱5.8B total · 9 flags

Other projects by this contractor

View all 82 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

October 16, 2023

Target End

April 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.