Flood Control and Drainage24FO0086

ORGANIZATIONAL OUTCOME 2- PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PINANGANURAN RIVER FLOOD CONTROL STRUCTURE ALONG SPILLW

ORGANIZATIONAL OUTCOME 2- PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PINANGANURAN RIVER FLOOD CONTROL STRUCTURE ALONG SPILLW is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱144,750,000.00. Status: Reported complete (DPWH). Contractor on record: RAMARPLUS INC FORMERLY RAMAR ENT. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Nasisi River Flood Mitigation Structure, Barangay Nabonoton, Ligao City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

82 projects · ₱5.8B total · 9 flags

4. Implementation

Contract Amount

₱144,750,000.00

Progress

Reported complete (DPWH)

Start Date

May 8, 2024

Target End

March 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.