Flood Control and Drainage20F00144

REHABILITATION/RESTORATION OF WARAS RIVER FLOOD CONTROL PROJECT, (SAN ISIDRO - SAGRADA SECTION), IRIGA CITY, CAMARINES SUR, CAMARINES SUR 5TH LEGISLATIVE DISTRICT

REHABILITATION/RESTORATION OF WARAS RIVER FLOOD CONTROL PROJECT, (SAN ISIDRO - SAGRADA SECTION), IRIGA CITY, CAMARINES SUR, CAMARINES SUR 5TH LEGISLATIVE DISTRICT is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱181,485,668.32. Status: Reported complete (DPWH). Contractor on record: RAMARPLUS INC FORMERLY RAMAR ENT. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

82 projects · ₱5.8B total · 9 flags

4. Implementation

Contract Amount

₱181,485,668.32

Progress

Reported complete (DPWH)

Start Date

March 8, 2021

Target End

January 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.