Rehabilitation / Major Repair of Drainage Structure24OE0116

Rehabilitation of Drainage System at Zone 41-57 (Phase 3), Manila City

Rehabilitation of Drainage System at Zone 41-57 (Phase 3), Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱29,086,241.46. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0002185

₱40,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008748

₱1,545,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008763

₱142,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱29,086,241.46

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

March 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.