Flood Control and Drainage19PB0017

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF NABUANGAN (DOWNSTREAM) FLOOD CONTROL, BRGY. RIPANG, CONNER, APAYAO

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF NABUANGAN (DOWNSTREAM) FLOOD CONTROL, BRGY. RIPANG, CONNER, APAYAO is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱14,258,711.27. Status: Reported complete (DPWH). Contractor on record: OMENGAN CONST. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROXIII-19-0006576 · ₱44,912,000 · release to the district office, not itemized per project

    Possible match · score 0.79

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱14,258,711 · OMENGAN CONST & DEVELOPMENT CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-05-01 → 2025-04-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Cagayan

Based on the coordinates published with the DPWH record and NOAH file Cagayan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF NABUANGAN (DOWNSTREAM) FLOOD CONTROL, BRGY. RIPANG, CONNER, APAYAO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-19-0006576

₱44,912,000.00 · FY2019

Released to Apayao 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱14,258,711.27 · OMENGAN CONST & DEVELOPMENT CORP

Award / contract ref: 19PB0017

Contractor

Not graded

62 projects · ₱4.2B total · 0 flags

Other projects by this contractor

No sat.

CONST/IMPVT OF ACCESS RDS LEADING TO AIRPORTS, SEAPORTS, AND DTD, CUDOG-MUNGAYANG-KIANGAN ROAD LEADING TO AMBUAYA LAKE, YAMASHITA SHRINE, AND KIYANGAN SETTLEMENT, KIANGAN AND LAGAWE, IFUGAO (INCLUDING CONSTRUCTION OF BRIDGES)

Cordillera Administrative Region, Cordillera Administrative Region

2016₱188.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONST. OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, ASIN - NANGALISANJCT. - BAYABAS - MONGLO JCT. (SECTION 1)

Cordillera Administrative Region, Cordillera Administrative Region

2020₱173.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION AND MAINTAINANCE OF BRIDGE ALONG NATIONAL ROADS CONSTRUCTION OF NEW PERMANENT BRIDGE TABBAYAGAN BRIDGE ALONG APAYAO-ILOCOS NORTE ROAD

Cordillera Administrative Region, Cordillera Administrative Region

2017₱154.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ASSET PRESERVATION - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANUEL S. AGYAO BOULEVARD-K0499 + 908 -K0500 + 467, K0508 + 130 - K0509 + 351

Lower Kalinga DEO, Cordillera Administrative Region

2024₱152.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND EMBANKMENT OF DIKE AND CHANNELING ALONG CHICO RIVER, TABUK CITY, KALINGA

Cordillera Administrative Region, Cordillera Administrative Region

2023₱144.8M
Past target date (DPWH On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0616+000 - K0619+750

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.7M
Reported complete (DPWH)
View all 62 projects →

4. Implementation

Contract Amount

₱14,258,711.27

Progress

Reported complete (DPWH)

Start Date

June 6, 2019

Target End

December 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Cordillera Administrative Region (CAR)ApayaoConner
Storms whose wind field reached it
Peilou 2026Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.